Plans for Coke/Carbon site remediation are unveiled

Project to cost $5.3M, take about 6 months

TERRE HAUTE — A $5.3 million project to remediate 20 acres of the former Terre Haute Coke and Carbon site at 13th and Hulman Streets is scheduled to begin June 1.

Site preparation, such as mobilizing equipment and installing mobile work offices, is set to start in mid May, officials with HIS Constructors Inc. reported in a construction coordinating meeting Thursday at Terre Haute City Hall.

“This will be a five- to six-month project, with about three-and-a-half months of excavation,” said Jay Geise, vice president of HIS Constructors, based in Indianapolis. The company was awarded a $2.7 million project in December to clear the site at 13th and Hulman streets.

Between 1,800 and 2,000 tons of soil will be removed per day. The soil will be hauled to and disposed of at the Sycamore Ridge Landfill in southern Vigo County. About $2.6 million of the project is to be paid to Republic for disposal.

The brownfield project, funded through the Indiana Brownfield Program and the Indiana Finance Authority, will remove about 80,000 cubic yards of soil contaminated with tar, arsenic, lead, naphthalene, benzo(a)pyrene and other hazardous substances.

(Brownfield is defined by The Free Dictionary online as: “A piece of industrial or commercial property that is abandoned or underused and often environmentally contaminated, especially one considered as a potential site for redevelopment.”)

While a trucking route has not yet been determined, it is estimated that trucks will take 75 minutes to haul to and from the landfill, with an additional 15 minutes at the landfill.

The project includes frontage along 13th Street to a setback extending 325 feet east of the property boundary and the Hulman Street frontage to a setback extending 325 feet south of the property boundary.

Excavation is planned to start on the northeast corner of the site along Hulman Street and continue in an “L” shape, ranging in depth from 6 to 8 feet or as shallow as 1 foot. The project includes the demolition and removal of any subsurface structures such as foundations, bricks, pipes or pits.

Those structures would be removed to a depth of 10 feet, Geise said.

Work at the site will be conducted 7 a.m. to 5 p.m. Monday through Friday.

A borrow site to replace soil will be determined in the next three to four days, said Brian Keeney, vice president of environmental operations for HIS Constructors. The city offered the use of 1,000 yards of extra dirt expected from a Hulman Lake dam project, which includes work to the dam’s emergency spillway.

Steven Standford, senior project manager for Weaver Boos Consultants, a construction and quality oversight firm for the city, said soil from the Hulman Lake dam and any soil from a borrow site must be tested. Standford also said his firm will closely monitor dust and dirt control at the site. Standford said the area has a sandy soil base, and he does not expect dust/dirt to be a problem.

A 6-foot security fence will surround the site during excavation.

In addition, a one-third mile, 10-foot wide asphalt trail will be installed along 13th Street. Pat Martin, chief planner for the city of Terre Haute, said the trail is a cost-effective way to cap the ground which is near an underground natural gas pipeline.

The site, which originally included 52 acres, was used as a coke and manufactured gas production facility from 1926 to 1988. The site manufactured 150,000 tons of high-carbon coke per year, with about 70 percent of the coke shipped to gray iron foundries. The city now owns 49 acres of the brownfield site.

Reporter Howard Greninger can be reached at 812-231-4204 or howard.greninger@tribstar.com

1
Text Only | Photo Reprints
Local & Bistate
Latest News
TribStar.com Poll
AP Video
Two Women Narrowly Avoid Being Hit by Train Raw: Japanese Soldiers Storm Beach in Exercises Girl Struck by Plane on Florida Beach Dies Raw: 2 Shells Hit Fuel Tank at Gaza Power Plant Rodents Rampant in Gardens Around Louvre Raw: Massive Explosions From Airstrikes in Gaza In Virginia, the Rise of a New Space Coast Boater Rescued From Edge of Kentucky Dam Raw: Rocket Launches Into Space With Cargo Ship Kerry: Not Worried About Israeli Criticism Raw: Weapons Fire Hits UN School in Gaza US Ready to Slap New Sanctions on Russia Crayola Announces Family Attraction in Orlando Broken Water Main Floods UCLA Raw: NH Man Held on $1M in Teen's Kidnapping House to Vote on Slimmed-down Bill for Border Looming Demand Could Undercut Flight Safety Raw: Earthquake Rocks Mexico's Gulf Coast Fox Dons 'Bondage Strap' Skirt at Comic-Con Raw: Otters Enjoy Water Slides at Japan Zoo
NDN Video
Heartwarming 'Batkid Begins' Documentary is Tear-Jerker Sadie Doesn't Want Her Brother to Grow Up Chapter Two: Designing for Naomi Watts Broken Water Main Floods UCLA "Maxim" Hotness! See Jessica Alba's Sizzling Spread Two women barely avoid being hit by train Orlando Bloom and Justin Bieber Reportedly Came To Blows In Ibiza Meet the Man Behind Dumb Starbucks Chris Pratt Adorably Surprises Kids at a 'Guardians of the Galaxy' Screening NOW TRENDING: Peyton Manning dancing at practice "The Bachelorette" Makes Her Decision Thieves pick the wrong gas station to rob Golden Sisters on '50 Shades' trailer: 'Look At That Chest!' Staten Island Man's Emotional Dunk Over NYPD Car - @TheBuzzeronFOX GMA: Dog passes out from excitment to see owner Baseball Hall of Famers Inducted 'Hunger Games: Mockingjay Part 1' Sneak Peek Florida Keys Webcam Captures Turtles Hatching Morgan Freeman Sucks Down Helium on 'Tonight Show' Robin Wright Can Dance! (WATCH)
Parade
Magazine

Click HERE to read all your Parade favorites including Hollywood Wire, Celebrity interviews and photo galleries, Food recipes and cooking tips, Games and lots more.
  • -

     

    March 12, 2010

activity